Report_Id: 245343 Est NO 0001 |
Date:12/09/2024 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 245343 | Estimate Number | 0001 | Estimate Type | PROGRESS | ||
District Office | MANCHESTER (11320) Perkins, Robert W. | ||||||
Contractor | BUSH & BURCHETT INC | ADDR SN 0 VC Code KY0022414 | |||||
PO BOX 400 | |||||||
ALLEN , KY , 41601 | |||||||
Pay Period | 05/30/2024 TO 11/17/2024 | ||||||
Date Approved | 11/25/2024 | ||||||
Primary Proj Number | BR04812542400 | ||||||
Project No. | STP BRZ 9030 (458) | ||||||
Primary County | HARLAN | ||||||
Name of Road | KY 1254 | ||||||
Description | ADDRESS DEFICIENCIES OF BRIDGE ON KY 1254 OVER POOR FORK CUM BERLAND RIVER (048B00091N) | ||||||
Date Let | 04/25/2024 | Formal Acceptance | |||||
Date Awarded | 05/07/2024 | Date Work Began | 11/11/2024 | ||||
Date Contract Executed | 05/30/2024 | Open To Traffic | |||||
Date NTP Issued | 05/30/2024 | Actual Completion Date | |||||
Current Contract Amount | $2,393,749.94 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $2,393,749.94 |
Total Earnings | $59,000.00 |
$0.00 |
$59,000.00 |
|
Percent Complete | 2.46 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $2,334,749.94 |
Gross Earnings | $59,000.00 |
$0.00 |
$59,000.00 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $59,000.00 |
$0.00 |
$59,000.00 |
|||
Contract Id | 245343 | Change Order Summary |
County | HARLAN | ||||||
Estimate Nbr | 0001 | Project Number | STP BRZ 9030 (458) | |||||||
Contractor | BUSH & BURCHETT INC | Period | 05/30/2024 TO 11/17/2024 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 245343 | COMMONWEALTH OF KENTUCKY |
County | HARLAN | ||||||
Contract Type | BRRL BRIDGE REPLACEMENT | TRANSPORTATION CABINET |
Primary Project Number | BR04812542400 | ||||||
Estimate Nbr | 0001 | Period | 05/30/2024 TO 11/17/2024 | |||||||
Contractor | BUSH & BURCHETT INC | |||||||||
Project | BR04812542400 | Fed/State Project Number | STP BRZ 9030 (458) | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | BR04812542400 | Fed/State Project Number | STP BRZ 9030 (458) | Category | 0001 PAVING | |||||||
0005 | DGA BASE | 00001 | TON | 161.00 | 161.000 | 0.000 | 0.000 | 50.00 | 0.00 | |||
0010 | CL2 ASPH BASE 0.75D PG64-22 | 00221 | TON | 150.00 | 150.000 | 0.000 | 0.000 | 270.00 | 0.00 | |||
0015 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 35.00 | 35.000 | 0.000 | 0.000 | 355.00 | 0.00 | |||
0020 | ASPHALT MATERIAL FOR TACK NON-TRACKING | 24970EC | TON | 0.35 | 0.350 | 0.000 | 0.000 | 10.00 | 0.00 | |||
Project | BR04812542400 | Fed/State Project Number | STP BRZ 9030 (458) | Category | 0002 ROADWAY | |||||||
0025 | STORM SEWER PIPE-18 IN | 00522 | LF | 115.00 | 115.000 | 0.000 | 0.000 | 234.00 | 0.00 | |||
0030 | PIPE CULVERT HEADWALL-18 IN | 01204 | EACH | 1.00 | 1.000 | 0.000 | 0.000 | 4,820.00 | 0.00 | |||
0035 | DROP BOX INLET TYPE 13G | 01559 | EACH | 1.00 | 1.000 | 0.000 | 0.000 | 4,860.00 | 0.00 | |||
0040 | STANDARD CURB AND GUTTER | 01810 | LF | 67.00 | 67.000 | 0.000 | 0.000 | 82.00 | 0.00 | |||
0045 | DELINEATOR FOR GUARDRAIL BI DIRECTIONAL WHITE | 01987 | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 25.00 | 0.00 | |||
0050 | CEM CONC ENT PAVEMENT-8 IN | 02101 | SQYD | 13.30 | 13.300 | 0.000 | 0.000 | 84.00 | 0.00 | |||
0055 | GUARDRAIL-STEEL W BEAM-S FACE A | 02355 | LF | 130.00 | 130.000 | 0.000 | 0.000 | 85.00 | 0.00 | |||
0060 | GUARDRAIL TERMINAL SECTION NO 1 | 02360 | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 200.00 | 0.00 | |||
0065 | EDGE KEY | 02585 | LF | 52.00 | 52.000 | 0.000 | 0.000 | 86.12 | 0.00 | |||
0070 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 0.500 | 0.000 | 0.500 | 6,000.00 | 3,000.00 | 3,000.00 | |
0075 | PORTABLE CHANGEABLE MESSAGE SIGN | 02671 | EACH | 2.00 | 2.000 | 2.000 | 0.000 | 2.000 | 3,000.00 | 6,000.00 | 6,000.00 | |
0080 | SIDEWALK-4 IN CONCRETE | 02720 | SQYD | 39.00 | 39.000 | 0.000 | 0.000 | 76.00 | 0.00 | |||
0085 | STAKING | 02726 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 10,000.00 | 0.00 | |||
0090 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 780.00 | 780.000 | 0.000 | 0.000 | 1.50 | 0.00 | |||
0095 | W CAP EXISTING MAIN | 14003 | EACH | 1.00 | 1.000 | 0.000 | 0.000 | 2,200.00 | 0.00 | |||
0100 | W METER RELOCATE | 14030 | EACH | 1.00 | 1.000 | 0.000 | 0.000 | 2,500.00 | 0.00 | |||
0105 | W STRUCTURE REMOVAL EX Water Vault Removal | 14088 | EACH | 1.00 | 1.000 | 0.000 | 0.000 | 1,800.00 | 0.00 | |||
0110 | W LINE STOP SIZE 1 | 14163 | EACH | 1.00 | 1.000 | 0.000 | 0.000 | 1,800.00 | 0.00 | |||
0115 | REMOVE & RELOCATE SIGNS | 20418ED | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 300.00 | 0.00 | |||
0120 | REMOVE SIGN | 21373ND | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 200.00 | 0.00 | |||
0125 | EROSION CONTROL | 21415ND | LS | 1.00 | 1.000 | 0.000 | 0.000 | 15,000.00 | 0.00 | |||
0130 | DETECTABLE WARNINGS | 23158ES505 | SQFT | 10.00 | 10.000 | 0.000 | 0.000 | 50.00 | 0.00 | |||
Project | BR04812542400 | Fed/State Project Number | STP BRZ 9030 (458) | Category | 0003 BRIDGE - 048B00091N | |||||||
0135 | FENCE-4 FT CHAIN LINK | 02273 | LF | 242.20 | 242.200 | 0.000 | 0.000 | 135.00 | 0.00 | |||
0140 | REMOVE CONCRETE MASONRY | 02403 | CUYD | 12.90 | 12.900 | 0.000 | 0.000 | 500.00 | 0.00 | |||
0145 | REMOVE STRUCTURE | 02731 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 165,000.00 | 0.00 | |||
0150 | ARMORED EDGE FOR CONCRETE | 03299 | LF | 53.20 | 53.200 | 0.000 | 0.000 | 125.00 | 0.00 | |||
0155 | STRUCTURE EXCAV-SOLID ROCK | 08002 | CUYD | 189.00 | 189.000 | 0.000 | 0.000 | 50.00 | 0.00 | |||
0160 | FOUNDATION PREPARATION | 08003 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 200,000.00 | 0.00 | |||
0165 | CYCLOPEAN STONE RIP RAP | 08019 | TON | 1,147.00 | 1,147.000 | 0.000 | 0.000 | 65.00 | 0.00 | |||
0170 | TEST PILES (REVISED 4-22-24) | 08033 | LF | 48.00 | 48.000 | 0.000 | 0.000 | 300.00 | 0.00 | |||
0175 | PRE-DRILLING FOR PILES | 08039 | LF | 108.00 | 108.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0180 | PILES-STEEL HP12X53 (REVISED 4-22-24) | 08046 | LF | 190.00 | 190.000 | 0.000 | 0.000 | 80.00 | 0.00 | |||
0185 | PILE POINTS-12 IN | 08094 | EACH | 12.00 | 12.000 | 0.000 | 0.000 | 150.00 | 0.00 | |||
0190 | CONCRETE-CLASS A | 08100 | CUYD | 276.90 | 276.900 | 0.000 | 0.000 | 1,000.00 | 0.00 | |||
0195 | CONCRETE-CLASS AA | 08104 | CUYD | 279.70 | 279.700 | 0.000 | 0.000 | 1,400.00 | 0.00 | |||
0200 | STEEL REINFORCEMENT | 08150 | LB | 20,812.00 | 20,812.000 | 0.000 | 0.000 | 2.00 | 0.00 | |||
0205 | STEEL REINFORCEMENT-EPOXY COATED | 08151 | LB | 84,752.00 | 84,752.000 | 0.000 | 0.000 | 2.00 | 0.00 | |||
0210 | CONCRETE SEALING | 23378EC | SQFT | 15,995.00 | 15,995.000 | 0.000 | 0.000 | 2.00 | 0.00 | |||
0215 | DECK DRAIN | 23813EC | EACH | 5.00 | 5.000 | 0.000 | 0.000 | 1,000.00 | 0.00 | |||
0220 | PPC I-BEAM TYPE HN 36-49 | 23963EC | LF | 953.40 | 953.400 | 0.000 | 0.000 | 600.00 | 0.00 | |||
0225 | RAIL SYSTEM TYPE T631 | 24896ED | LF | 484.40 | 484.400 | 0.000 | 0.000 | 150.00 | 0.00 | |||
Project | BR04812542400 | Fed/State Project Number | STP BRZ 9030 (458) | Category | 0004 DEMOBILIZATION & MOBILIZATION | |||||||
0230 | MOBILIZATION | 02568 | LS | 1.00 | 1.000 | 0.500 | 0.000 | 0.500 | 100,000.00 | 50,000.00 | 50,000.00 | |
0235 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 34,000.00 | 0.00 | |||
SUBTOT | $59,000.00 |
$59,000.00 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |